Project planning – schedule and cost

When looking at the life of a project plan, it is useful to graph and outline the cost variance (CV), and schedule variance (SV). Determining progress, or lack of progress, provides essential information to assess a given project. 

Complete exercise 2 in chapter 13 of the textbook. Given the data provided, in an excel spreadsheet, PowerPoint, or other appropriate method of delivery, determine the following:

1.  Schedule Variance (SV)

2.  Cost Variance (CV)

3.  Schedule Performance Index (SPI)

4.  Cost Performance Index (CPI)

In 250-300 words, answer the questions provided with the exercise. Reflect on the assessment of this project assessment. Should the project continue to improve? 

Exercise 2 Question

On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?

Expert paper writers are just a few clicks away

Place an order in 3 easy steps. Takes less than 5 mins.

Calculate the price of your order

You will get a personal manager and a discount.
We'll send you the first draft for approval by at
Total price:
$0.00